New Hunt nearly 98 percent complete

Construction is nearly 98 percent complete at Hunt. Workers prepare the football and soccer fields for installation of the synthetic turf. At the softball field, workers have constructed curb around the synthetic turf outfield. Backstop fencing framing and the layout for the baseball diamond, bases and dugout are complete.

Remaining curbs, gutters and sidewalks are now 95 percent complete. All asphalt paving on site will be complete by July 12.

Inside the building, workers finished installing the gym floor and bleachers. Furniture and equipment were delivered to the school. Hunt staff will move into their new school starting Aug. 9.

Hunt backstop softball

Translate Our Website

Translate this page by clicking the flag button in the bottom right corner and selecting your preferred language.

Traduzca esta página haciendo clic en el botón de la bandera en la esquina inferior derecha y seleccionando su idioma preferido.

បកប្រែទំព័រនេះដោយចុចប៊ូតុងទង់នៅក្នុងជ្រុងខាងស្តាំខាងក្រោមនិងជ្រើសរើសភាសាដែលអ្នកចូលចិត្តរបស់អ្នក។

Dịch trang này bằng cách nhấp vào nút gắn cờ ở góc dưới cùng bên phải và chọn ngôn ngữ ưa thích của bạn.

오른쪽 하단에 있는 플래그 버튼을 클릭하고 원하는 언어를 선택하여 이 페이지를 번역합니다.

Перекладіть цю сторінку, натиснувши кнопку прапора в нижньому правому куті та вибравши потрібну мову.

Переведите эту страницу, нажав на кнопку с флагом в правом нижнем углу и выбрав желаемый язык.

Contact Us

Our Communications Department serves as a liaison to the community and provides various services to promote effective communication and partnerships. Contact us by email at info@tacoma.k12.wa.us or by phone at 253-571-1015.

Media Requests

Tanisha Jumper
Chief Communications Officer
253-571-1015
tjumper@tacoma.k12.wa.us

Kathryn McCarthy
Assistant Director of Communications
253-571-1015
kmccart@tacoma.k12.wa.us